Power Delivery Project

115 kV Transmission Line and Substation

Shooting Star

Blattner Energy self-performed the complete electrical scope of work for a 104-MW wind farm, also constructed by Blattner, including material procurement and construction of a 115-kV substation and 5.6 miles of 115-kV single circuit transmission line.

Delays by material and equipment suppliers condensed the construction schedule to the point where 70 percent of the transmission work and 90 percent of the substation work had to be completed and tested within 30 days. Due to extensive communication and coordination efforts between Blattner and the project developer, the substation was energized as planned and the project was completed on schedule.

Client: Confidential Client
Location: Kansas
Size: 115-kV Transmission Line & Collector Substation
Status Completed